Program Status
ON TRACK
Go-Live Target
Aug 15, 2026
Projected Go-Live
Aug 15, 2026
Schedule Variance
0 days
Budget
$2.4M / $2.8M
Open Risks
5
ⓘ
Click any milestone bar to simulate a delay and watch the cascade ripple through dependent tasks.
Critical Path & Dependencies
Milestone
Critical Path
Non-Critical
Completed
Delayed (simulated)
Cascade Impact
Risk Register
| ID | Risk | Category | Likelihood | Impact | Score | Mitigation | Owner | Status |
|---|